Excavating begins

Excavating begins

Pete O'Keefe of O’Keefe Construction breaks first ground. The topsoil is stockpiled on site and goes into the green roofs and berms next spring.

Getting it right

Getting it right

John O'Keefe and Dennis Purinton get down on the plans. 80% of this slab on grade house is Thermomass concrete, and there is no room for error.

Thumbs up

Thumbs up

Mike Purinton calls in the mixer to pour the Thermomass frost walls. 4” XPS foam insulation mates with the sub slab XPS for complete thermal break

Top down

Top down

Drone's eye view of the foundation, with plumbing and electrical conduit in place. This photo was taken just four weeks after breaking ground.

Setting in

Setting in

Master Plumber Jeff Shaw, CM John O'Keefe, Lead Carpenter John Bates and Master Plumber Steve Osella work on the sub-slab utilities. 

Future-proof

Future-proof

Hot and cold water PEX supply lines will run free inside flexible polyethylene pipe, which is encased in 4" foam sleeves under the slab insulation, and in rigid conduit through the slab. The large conduit under the elbows is an electrical/data trunk. Once buried in concrete, these utility lines can be upgraded without too much fuss in the future.

Pouring it on

Pouring it on

Dennis Purinton guides the fiber-reinforced pour from Tilcon. Four inches of concrete over four inches of XPS foam rest on three feet of compacted stone and vapor barrier. When finished, the entire first floor becomes a thermal sink, moderating indoor temperatures throughout the year.

A Beautiful Slab

A Beautiful Slab

The cured slab and utility stubs are ready to be wrapped up for the winter. Come spring we'll be ready to pour the walls.

Team Huddle

Team Huddle

Master Carpenter John Bates, CM John O'Keefe and Kris Carr of Carr Concrete double check plans before the walls go up.

Forming Walls

Forming up for Thermomass (VIDEO)

Future Green

Future Green

Joists from CanAm Steel support the garage green roof. Metal decking, 4” of concrete, 2” XPS foam insulation, drainage mat, sand and soil will complete the structure. Fiberglas form ties for the walls haven’t been trimmed yet.

Framing Up

Framing Up

Gable ends are framed to match the main roof trusses, 3,500 lb Douglas Fir assemblies designed and cut by Vermont Timber Frames.

Neopor SIPs

Neopor SIPs

Structural Insulated Panels, also designed and made by Vermont Timber Frames, are cored with graphite-infused Neopor, creating a tight R54 roof.

Working Stone

VIDEO: Local stone gets some engineering to provide veneers and a hearth.

View from the South

View from the South

Terra Cotta and Regal White steel siding from Drexel Metals wrap the Pella Impervia windows and doors. The 10Kw LG solar array from Waldo Renewable is grid-tied and battery-ready.

On with the Roof

On with the Roof

Steel roof panels from Drexel Metals being installed By J. A. Deniger’s crew.

The Trusses

The Trusses

Each of the five massive roof trusses from Vermont Timber Frames weighs about 3,500 Lbs. Two runs of LVL header beam work as a sill plate to spread the load on the Thermomass walls. 14”x1” EPDM sill gasket assures air tightness.

Building Solar

VIDEO: Waldo Renewable installs a 10Kw LG array and SolarEdge Inverter system.